The combined thermal power, process-controlled power plant PM 4 comprises 1 steam boiler with a capacity of
32 t/h and 1 back-pressure steam generator with a capacity of 3,100 kW. The fulfilment of demand of the total power requirement from the self-energy production amounts to 40 %.
Our combined thermal power, process-controlled, combined-cycle thermal power plant PM 2 (GuD process) comprises 1 gas generator: 4,500 kW, 1 steam boiler with a capacity of 45 t/h, 1 steam generator: 3.800 kW and additional 3 superheated steam boilers with a capacity of 20,5 t/h per unit.
In one of the superheated steam boilers the biogas produced in the waste water treatment plant is recycled. In this case the fulfilment of demand of the total power requirement from the self-energy production amounts to
65 %.